Greenpeace reaction to France’s nine-month nuclear delay

Thu, Aug 28, 2008

Just nine months into construction, Areva’s new flagship nuclear reactor is already nine months behind schedule. This delay echoes the problems at Areva’s previous site in Olkiluoto, Finland, where construction is more than two years behind schedule, more than 2 billion Euro over budget and beset with safety problems.

"Clearly Areva has learnt nothing from the ongoing problems at Olkiluoto" said Jan Beranek, Greenpeace International nuclear campaigner, reacting to the news that construction work on the Flamanville reactor is also running behind schedule.

French newspaper Le Canard Enchaine reports that problems with concrete pouring and the reactor liner have led to the delay. These mirror the problems at the Olkiluoto 3 construction site.

"Construction at Flamanville should be abandoned" concluded Beranek. "France would be better served with investments in safe, clean renewable energy and energy efficiency as described in the Greenpeace Energy [R]evolution scenario"

Source: Greenpeace

Tags: greenpeace  finland  safety  french  investments 
Post to: DiggDigg, RedditReddit, SlashdotSlashdot,
0 Comment(s). Post a comment
Add your comment

Code        

 

  Other Articles :

  

BASF is leading in disclosure about climate protection

  

EPA Picks Cleanup Plan for South Minneapolis Superfund Site

  

Creation of Global Biofuels Industry Will Be Far More Difficult than Previously Thought, Accenture Study Finds

  

» Greenpeace reaction to France’s nine-month nuclear delay

  

Greenpeace urges governments to speed up climate negotiations

  

Public involvement usually leads to better environmental decision making

  

Multiple Polar Bears Discovered Swimming Many Miles from Alaska Coast

 
© TAUME.COM